Senior Center Project
The floor has been completely poured and they are
working on the parking lot grading. The ICF – or insulated concrete
forms – have been delivered for the walls.
    _small.JPG)  _small.JPG) _small.JPG) 
Community Library Project
The footings passed inspections and will soon be
poured. They are continuing to form the west walls of the basement and
the elevator shaft.
 _small.JPG) _small.JPG) _small.JPG)  _small.JPG) _small.JPG) _small.JPG)
Pool Splash Pad Project
The textured and colored concrete has been poured at
the splash pad. They are working to have the parameter concrete poured
and putting fence posts in.
   _small.JPG)
Karla Avenue Project
Karla is now
finished up to the railroad overpass.
_small.JPG) _small.JPG) 
|